TOTAL FREE HEALTH AND SAFETY DOCUMENTS DOWNLOADING SOURCE

 


Breaking

Sunday, October 22, 2023

HSE DOCUMENTS-LUMINARIES INSTALLATION AND TESTING CHECKLIST

 

HSE DOCUMENTS-LUMINARIES INSTALLATION AND TESTING CHECKLIST

Luminaries Installation and Testing Checklist


1. Ensure the [Project/Location Name Here] installation details and installed in its final location as per the drawings.

2. Ensure Emergency Luminaires are installed as per issued drawings approved by Local civil Defense regulations.

3. Installation details of each luminary or wiring (if converted fitting) are available.

4. Ensure all the luminaries are installed in their final location as per drawings.

5. Ensure Exit/ Escape route fittings are installed as per Local Civil defense regulations.

6. Ensure the rotation of the installed Emergency Luminaries is as per min, lux level requirements are per BSEN Standards and Local Civil Defense regulations.

7. Disconnect Circuits from [Project/Location Name Here] and connect Temp. The power supply of 230V ac, 50 Hz from local MCB/ ELCB in order to eliminate short circuits/Earth faults in the wirings.

8. Ensure during this above test, that all the lamps are on condition, if not rectify the same.

9. After the above circuit test results are satisfactory, connect back all the circuits to [Project/Location Name Here].

10. Ensure all the [Project/Location Name Here] are connected to the Inverter Panel as per the drawing

11. Ensure all the [Project/Location Name Here] have at least one local DB Input as part of sub-circuit monitoring.

12. Sensing supplies are provided in the [Project/Location Name Here].

13. Has the Pre-commissioning meeting taken place with the contractor (If yes, Date:  And if any points are added. Discussed (provide report or details)

14. Has the Second Pre-commissioning meeting taken place with the contractor (If yes Date:  And if any add. points discussed (provide  report or details)

Download File Now

No comments: