OUTLINE FOR THE FINAL DISTRIBUTION BOARD
1. Verify the Installed Distribution Boards have approved submittals.
2. Ensure the drawings used for installation are correct and approved.
3. Check and make sure the Distribution Boards are new and undamaged.
4. Check the DBs as per the approved load schedule and drawings.
5. Check the Nameplate and identification labels as per the Load schedule and approved submittals.
6. Check the DBs have rigid support.
7. Make sure location Distribution Boards are as per the approved drawing.
8. Check the termination and dressing of cables and wires completed neatly.
9. All cables and wires including grounding are terminated and identified.
10. Make sure all terminals are tightened and secured as required.
11. Ensure DB's interiors are cleaned and free from dust.
12. Check the grounding has been provided as per the approved drawing including the body of the Dbs.
13. Identification provided as specified/required