Method Statement for Installation of Glazed Partitioning Glass Office Partitions:
Introduction:
This method statement outlines the installation procedure for glazed partitioning glass office partitions. The partitions will be installed to divide the office space into separate rooms. The installation will be conducted as per the manufacturer's recommendations and industry standards.
Site Preparation:
Before installation, the site must be prepared to receive the glazed partitions. The site should be clean and free from obstructions. All necessary tools and equipment required for the installation should be available and in good working condition. Adequate access and space should be provided for the installation team to work.
Installation Procedure:
The installation procedure will involve the following steps:
Step 1: Measurement and Survey
The installation team will carry out a detailed survey of the site to determine the exact dimensions required for the partitions. Accurate measurements will be taken to ensure that the partitions fit perfectly into the designated spaces.
Step 2: Preparation of Partitioning Materials
The glazed partitions will be manufactured offsite, and the installation team will ensure that they are delivered to the site in good condition. The team will prepare the necessary tools and equipment for the installation, including fixing brackets, screws, and sealant.
Step 3: Installation of Framing System
The framing system will be installed first. The team will fix the brackets onto the floor and ceiling, ensuring that they are level and plumb. The framing system will then be installed between the brackets, and the team will ensure that it is secure and stable.
Step 4: Installation of Glass Panels
Once the framing system is in place, the glass panels will be installed. The panels will be carefully lifted into place and secured using the fixing brackets. The team will ensure that the glass is level and that there are no gaps or spaces between the panels.
Step 5: Sealing and Finishing
Finally, the installation team will apply a sealant to the joints between the glass panels and the framing system. The sealant will be left to cure for the recommended time before any finishing work is carried out. Any excess sealant will be removed, and the partitions will be cleaned and inspected to ensure that they are free from defects.
Health and Safety:
During the installation, the team will ensure that all necessary health and safety precautions are taken. The team will wear appropriate PPE, and any hazardous materials or waste will be disposed of following relevant regulations. The installation team will also ensure that any risks to the public are minimized, and any necessary warning signs or barriers will be put in place.
Quality Control:
Quality control checks will be carried out at every stage of the installation process to ensure that the glazed partitions are installed to the highest standard. The installation team will check that all measurements are accurate, the framing system is secure, and the glass panels are level and without defects. Any issues identified will be rectified before the installation is signed off.
Conclusion:
This method statement outlines the procedure for the installation of glazed partitioning glass office partitions. The installation will be carried out following industry standards and the manufacturer's recommendations. All health and safety measures will be taken, and quality control checks will be carried out to ensure that the partitions are installed to the highest standard.