Here are some of the basic and initial points for the risk assessment while installation of sounding pipe inside the tank. for more health and safety free document download, you are requested to subscribe the blog and get the notifications for new uploaded documents.
1. Task Steps
- Pre-inspection/marking
- Fabrication of pipe spool on deck
- To cut pipe penetration on the main deck
- To weld double plate on the tank bottom
- To lower pipe to the tank
- Install pipe (bottom to top)
- Housekeeping
- Hazards
- Hit by object
- Fire explosion
- Pinch points
- Sharp edge
- Flying of objects
- Burnt
- Falling
- Tripping hazard
- Asphyxiation
- Electrical
- Struck by Cut against Falling Objects
Possible Accident/III Health & Persons at Risk
- Faint, lack of oxygen, overcome by gas
- Fatal Injury caused by a falling object, hit by the structure
- Fatal accident -Hand/Finger injuries
- Eye Injury
- Burnt injuries on hand
- Sprained or bruises.
- Fatal accident
- Injury caused by a falling object
- Sprained ankle
- Faint, lack of oxygen, overcome by gas
- Fatal electrocution from exposed electrical damaged cables, wet condition.
Existing Risk Control
- Valid entry permit
- Portable gas detector (working condition, calibrated, competent user)
- Dual badge system
- Highlight in Company/Organization's meeting
- Adapt 3-point contact while climbing the ladder
- Wear rubber boots
- The only explosion-proof lighting can be used
- Proper PPE (safety helmet)
- Valid hot work permit
- Qualified fire watch with working fire extinguisher/hose
- Maintain communication among co-workers
- Leather gloves
- Eye protection (safety goggles)
- Long sleeve with leather glove /foot protection
- Housekeeping, passageway clear
- Qualified fire watch with working fire extinguisher/hose
- Valid inspection tag
- Standby watchman at tank bottom
- Covered up the hole
- Valid entry permit
- Portable gas detector (working condition, calibrated, competent user)
- Buddy system
- Highlight in Organization’s meeting
- No damaged cable
- Condition dry (clothes dry)
- Maintain communication
- Remove sharp edge
- Valid Ok Tag
- No modification to scaffold
- Contain rubbish bag
- Secure all tools