Method Statement of Programming of Fire Alarm System for Interfacing Module.

METHOD STATEMENT

1.       Purpose

This document defines the method for Reprogramming of fire alarm system for interfacing module of AHU Unit and needs to check the exact fault of Annunciator-2 at (Project/Facility Name) and Annunciator.

2.       Scope

The scope of works detailed within this document applies to my method for Reprogramming for a fire alarm system for Interfacing module of AHU and need to check the exact fault of Annunciator-2 whereby upon satisfactory completion I inspection of works, following Project requirement and effective & efficient system is handed Over to the Client.

3.       Reference

  • NFPA 101Life Safety Code
  • NFPA 72 Fire alarm system
  • NFPA 70 (2014 Edition)- Electrical

4.       Procedure

Sr

Activity

Responsible Person

Controlling Document

Preventive maintenance:

1.  

Authorized PTW SHALL be Issued by the client before the start of works

Worksite Engineer

 

2.  

Personnel conducting works SHALL wear  appropriate PPE

 

 

3.  

Safety warning signs SHALL be provided and the area cleared of non-essential personnel

 

 

4.  

The programmer will connect the software with the fire alarm panel in MODE-1.

Worksite Engineer

 

5.  

The Programmer already added the existing interfacing module as per the fire alarm panel Node and they will provide cause and effect (During fire alarm activation AHU module will be activated after 180 sec time delay) for the Existing module.

 

 

6.  

The programmer will do the changing of caution and effect as per the site standard to activate the Existing module.

Worksite Engineer

 

7.  

After completing programming and updating the fire system. We need to do the alarm testing to check the cause and effect of the Exiting module.

 

 

8.  

The programmer will connect the software with fire alarm master panel in (specified Room) and he will check and troubleshoot exact fault of annunciator -2 Trouble.

 

 


 